    Bulawayo -Victoria Falls Road Reconstruction Gathers Pace

    Published on

    spot_img

    ‎Harare, (New Ziana) -The long-awaited rehabilitation of the Bulawayo–Victoria Falls Road is gathering momentum, with visible progress being recorded across multiple sections of the 435-kilometre highway, the government has said.

    ‎Posting on the National Development Strategy 1 (NDS1) X handle (formerly Twitter), the government said five contractors, Fossil Contracting, Masimba Contracting, Syvern Investments, Bitumen Resources, and Tensor Systems are currently on the ground, each upgrading a 50-kilometre stretch under the ambitious road reconstruction program of the government.

    According to progress reports, notable work has already been completed in several zones with ‎Fossil Contracting having cleared a 4 kilometre detour from the 48.6 km peg, Masimba Contracting has completed clearing 5 kilometres between the 85 km and 90 km marks while Syvern Investments has advanced between the 99.6 km and 104 km sections.

    Bitumen Resources has made headway with 4.2 kilometres cleared from the 201.6 km point while ‎Tensor Systems is also mobilising its teams for work on its allocated segment.

    Launched in June this year, the project is expected to be completed within ten months by February 2026, following a carefully coordinated kilometre-by-kilometre reconstruction plan.

    The upgraded highway will significantly improve transport efficiency and safety, boost tourism to the Victoria Falls area, and open new opportunities for trade along the key economic corridor, while the project is expected to create more than 2 000 jobs for local communities.

    The government has underscored the importance of the reconstruction effort, describing it as a vital component of Zimbabwe’s infrastructure modernisation under the National Development Strategy 1 (NDS1).

    ‎”The Bulawayo–Victoria Falls Road is one of the country’s most strategic routes, linking major tourism and trade centres. Its rehabilitation will drive regional connectivity and economic growth,” it said.

    ‎Once completed, the new-look highway is expected to transform travel between Bulawayo and Victoria Falls, turning what has long been a rough, time-consuming journey into a safer, smoother, and more efficient route for both tourists and transporters.

    New Ziana

    Latest articles

    KMC WINS THE COMMUNITY EMPOWERMENT AND SOCIAL IMPACT AWARD

    Kamativi Mining Company (KMC), a leading lithium producer, has been honored with the prestigious...

    ZIFA convenes club licensing regulations workshop

    Harare, (New Ziana) - The Zimbabwe Football Association (ZIFA) on Thursday convened a workshop...

    Government still pursuing establishment of Road Accident Fund

    Harare, (New Ziana) - The Zimbabwe government is expediting the establishment of the Road...

    Caledonia Mining Posts 467 percent Profit Surge

    Harare, (New Ziana) — Caledonia Mining Corporation recorded a dramatic 467 percent surge in...

    More like this

    KMC WINS THE COMMUNITY EMPOWERMENT AND SOCIAL IMPACT AWARD

    Kamativi Mining Company (KMC), a leading lithium producer, has been honored with the prestigious...

    ZIFA convenes club licensing regulations workshop

    Harare, (New Ziana) - The Zimbabwe Football Association (ZIFA) on Thursday convened a workshop...

    Government still pursuing establishment of Road Accident Fund

    Harare, (New Ziana) - The Zimbabwe government is expediting the establishment of the Road...
    error: Content is protected !!